CDBG Slurry Seal Coating Project 

Notice of Public Improvements 


​​Description of project: The repair of street sections, construction of access ramps, installation of crack, chip, and slurry seal; and striping on the following streets:

    • Broadmead St., Luder Ave., Doreen Ave, Delco Ave., and Thienes Ave.
    • Schmidt Rd., Luder Ave., Doreen Ave. and Delco Ave.






​Construction Schedule 

  September 4th - 8th    Contractor will administer spray and saw cut concrete for access ramps. 
  September 11th - 15th                      Removal and replacement of  concrete for access ramps, crack seal, and repair street section areas. 
  September 18th - 22nd     Installation of chip seal, slurry seal and adjust manholes. 
  September 25th - 29th     Adjust manholes, temporary striping (cat track).

For more information, contact:
    • Keith Fordham, Project Foreman  at (909) 973-7569 
    • Arjan Idnani , City Engineer at (626) 579-6540 Ext. 3203 