Updates/Schedule of
Durfee Avenue Street and Median Improvement Project

Click here for Project Overview 


     
   
     
   
  • March 6 - March 10, 2017 - ​Notices of Construction to residents and businesses delivered by contractor and project is mobilized. 
     
   
  • March 13 - March 17, 2017 - Removal of sidewalk and curb & gutter along Durfee Avenue  
     
   
  • March 20 - March 24, 2017 - ​Removal and replacement of driveways; and work on Bio Filters. 
     
   
  • March 27 - March 30, 2017 - Contractor will pour concrete on driveways and remove street planters​ 
     
   
  • April 3 - April 7, 2017 ​- Contractor will continue pouring concrete driveways as well as concrete cross gutter and drain under sidewalk. 
     
   
  • April 10 - April 14, 2017 - Contractor will pour concrete for driveways and access ramps; and work on under sidewalk drains. Contractor will also remove and replace planters on both sides of street and install irrigation line. One lane will be open for traffic on both sides of the street until May 29, 2017.
     
   
  • April 17​ -April 21, 2017 - Contractor to set traffic and survey work for the construction of medians. Will continue to pour concrete for planters on both sides of the street and continue to install irrigation line. One lane will be open for traffic on both sides of the street until May 29, 2017.
     
   
  • ​April 24 - April 28, 2017 - Contractor will remove and replace median and continue to install irrigation line in medians.  One lane will be open for traffic on both sides of the street until May 29, 2017.
     
   
  • May 1 - May 5, 2017 -  Contractor will install curbs along the medians, pavers inside the medians, irrigation in the medians and will work on bio-filter catch basins. 
     
   
  • May 15 - May 19, 2017 - Contractor will continue installing pavers inside the medians​, irrigation in the medians, and bio-filter catch basins. 
     
   
  • May 22 - May 26, 2017 - Contractor will continue installing pavers inside the median, irrigation, and landscaping in the medians, and bio-filter catch basins.​ 
     
   
  • May 29 - June 2, 2017  Contractor will  continue installing landscaping in the medians and will grind the street and install 2" asphalt. 
    • Expect Major Delays:
      • May 30th from 7:00 am to 4:30 pm for daytime pavement grinding 
      • May 31st & June 1st from 8:00 pm to 5:00 am for night paving. Street closure/detour from Rush St. to Michael Hunt Dr. 
     
   
  •  ​June 5 - June 9, 2017 - Contractor  will do landscaping and street striping. 
     
   
  • June 12- June 16, 2017 - Contractor is anticipated to do landscaping and slurry seal on Durfee Ave. (between Peck Rd. and Fawcett Ave.) and Striping. Installation of slurry seal on Tuesday, June 13th and Wednesday, June 14th along Durfee Avenue from Peck Road to west along South El Monte High School.
     
   
  • June 19- June 23, 2017 - Contractor will complete the landscaping and striping. This will complete the project.







      Project Contact Information: 

    • City's Engineering Department - Arjan Idnani (626) 579-6540 Ext 3203
    • On Site Project Inspector- Cris Cole (310) 525-0675
    • Contractor for Project- All American Asphalt (951) 736-7600